A
job was budgeted to require three hours of labor per unit at $12.50 per
hour. The job consisted of 8,000 units and was completed in 23,600
hours at a total labor cost of $345,600
| What is the labor rate variance? |
| → | $50,600 unfavorable |
| $5,000 favorable | |
| $45,600 unfavorable | |
| $50,600 favorable | |
| $5,000 unfavorable |