Use the following data to find the total direct labor cost
variance:
Direct labor standard (4 hrs.@ $ 7/hr.) $28per unit
Actual hours worked per unit 3.5 hours
Actual units produced 4,500 units
Actual rate per hour 7.25
_______________________
$11,813 unfavorable.
$18,000 unfavorable.
$18,000 favorable.
$13,500 favorable.
$11,813 favorable.
_______________
Comment
Direct labor standard (4 hrs.@ $ 7/hr.) $28per unit
Actual hours worked per unit 3.5 hours
Actual units produced 4,500 units
Actual rate per hour 7.25
_______________________
$11,813 unfavorable.
$18,000 unfavorable.
$18,000 favorable.
$13,500 favorable.
$11,813 favorable.
_______________
Best answer
Therefore the total direct labour
cost when rounded off would be $11,813(F), thus correct option is
5.